Pausing a migrate / store project stops a project with a recurring schedule, or a single run project scheduled for the future, from running. It does not remove the project from the list of projects on the Migrate / Store screen (see Figure 75).
Note: | Pausing a project does not cancel a job that is currently running. To cancel a migrate / store job that is currently running, see Cancel a Migrate / Store Job. |
To pause a migrate / store project, click Pause next to the project that you want to pause, select Pause Project Schedule from the Choose Action drop-down list, and click Submit.
To resume a paused project, see Resume a Migrate / Store Project.